上周四川地區(qū)持續(xù)高溫,成都日間氣溫最高突破39?℃,車間內部溫度更是超過40?℃。面對酷暑挑戰(zhàn),為了項目如期交付,公司生產部門頂住高溫,持續(xù)工作,多個大型變壓器項目依然有條不紊的進行中:
75000/220?kV 項目:第2臺高壓引線已裝配完畢,當前正進行低壓引線裝配,預計順利進入下一步驟。
同系列第1臺油箱已安全抵廠,正快速推進總裝與試驗進程。
70000/220?kV 項目:鐵心復位插片工序完成,即將進入整裝階段。
越西31500/110?kV 項目:鐵心疊片已全部就緒,下一步將開展繞組引線及烘干作業(yè)。
18900/110?kV 項目:鐵心剪片進行中,高壓及調壓繞組線圈已進入繞制階段,立式繞線模具也已完成清潔與調正就緒。
盡管處于極端高溫環(huán)境,公司生產線仍舊保持高效,節(jié)奏有序。生產團隊憑借標準化管理和精細化流程,在酷暑中保障工期和品質的雙重達成。成都雙星變壓器有限公司將繼續(xù)保持這種高效穩(wěn)定的生產節(jié)奏,確保所有交付任務精準兌現(xiàn),為全球客戶提供可靠的產品與服務。
感謝所有工作人員在艱苦環(huán)境下的堅持與貢獻,歡迎各界繼續(xù)關注我們的項目進展!
Last week, Sichuan experienced a prolonged heatwave with daytime temperatures in Chengdu soaring past 39?°C, and workshop temperatures exceeding 40?°C. In the face of this oppressive heat, our production teams stayed the course to ensure project schedules were met. Multiple large transformer projects remain progressing smoothly and systematically:
75,000/220?kV Project: The high-voltage lead assembly for the second unit is complete; low-voltage lead assembly is now underway, with the next steps on track.
First 75,000/220?kV Oil Tank: Has safely arrived at the factory and is quickly advancing toward final assembly and testing.
70,000/220?kV Project: Core lamination re-insertion is complete; the unit is now entering the full assembly phase.
Yuexi 31,500/110?kV Project: Core laminations are fully prepped, with winding and drying processes scheduled next.
18,900/110?kV Project: Core cutting is in progress; high-voltage and tap-changer winding coils are in production, and the vertical winding mandrel has been cleaned and realigned.
Despite the severe heat, our production lines maintain exceptional efficiency and order. Through rigorous management standards and precision-driven process control, we continue to meet both timelines and quality benchmarks. Chengdu Shuangxing Transformer Co., Ltd. remains fully committed to sustaining this high-performing production tempo, ensuring every delivery is precise—and every customer is satisfied.
We extend our gratitude to all team members for their dedication under challenging conditions, and warmly welcome our global partners to stay tuned to our project milestones!
- 2025-04公司動態(tài)|重載前行,穩(wěn)達山巔--260000kVA/220kV主變壓器穿越貴州山區(qū)運輸紀實
- 2025-04公司動態(tài)|重要節(jié)點 —— 第二臺260000/220kV主變順利交
- 2025-04公司動態(tài)|節(jié)后開工有序生產,嚴把質量高效交付
- 2025-04公司動態(tài) | 260000/220kV 變壓器順利通過測試并啟運交付
- 2025-02公司新聞 | 植物油變壓器出口瑞典,助力全球綠色能源發(fā)展
- 2024-11我公司造250000kVA/220kV自耦變壓器順利出廠發(fā)運吉爾吉斯斯坦
- 2024-03二三月生日團建會
- 2024-03縣領導李建康到成都雙星調研“開門紅”工作